Queensberry Footbridge, 2055 – Replacement Works
Church Street, Amesbury, Wiltshire, SP4 7EU
Our contractors are preparing to replace the above footbridge with site works starting 30th April 2018 (1st week of May).
The bridge replacement works are then expected to take 3 weeks to complete and SSE Contractors will be on site in advance of our works to temporarily remove overhead cabling. During the works pedestrians will be temporarily diverted onto the main highway bridge and traffic will be managed under 2-way temporary lights. We will require 2 x 1day full road closures to take out the existing footbridge and install the replacement footbridge. The closure dates will be advertised on site in advance and a diversion route will be implemented.